7 years after substantial completion of such improvement.
Exception:
If the claim arises during the 7th year of substantial completion, action can be brought within 1 year of the date of the injury, but no more than 8 years post substantial completion.
Disclaimer: This information was published on August 1, 2021. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Connecticut since that date. Visit our 50-State Construction Law Map for information on other states.