Commencement notice (Private): No.
Completion notice (Private): Optional.
Preliminary lien notice (Private): Prime contractor - Not required; Subcontractor - 31 days after first furnishing labor/materials.
Pre-lien notice (Private): Not required.
Lien claim (Private): 90 days after latest of completion of the project and last furnishing labor/materials by lien claimant.
Deadline to file suit (Private): 6 months after recording lien.
Bonding permitted (Private): Yes, must be 150% of the lien value.
Statutory lien waiver form (Private): Yes.
Special notes: Time period to file lien is reduced to 40 days if Notice of Completion is recorded.