Commencement notice (Private): No.
Completion notice (Private): No.
Preliminary lien notice (Private): Prime contractor - Not required; Subcontractor - Before commencing work.
Pre-lien notice (Private): Not required.
Lien claim (Private): Lien is automatically created by statute, no separate filing required.
Deadline to file suit (Private): 120 days after last furnishing labor/materials.
Bonding permitted (Private): Whether or not a bond is permitted is within the discretion of the Court.
Statutory lien waiver form (Private): No.
Special notes: Subcontractors are also required to furnish Owner an account of work performed every 30 days.
Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by New Hampshire since that date. Visit our 50-State Construction Law Map for information on other states.