Commencement notice (Private): No.
Completion notice (Private): No.
Preliminary lien notice (Private): Not required.
Pre-lien notice (Private): Prime contractor - Not required; Subcontractor - 75 days after last furnishing labor/materials.
Lien claim (Private): Prime Contractor - 4 months after last furnishing labor/materials; Subcontractor - 90 days after last furnishing labor/materials.
Deadline to file suit (Private): 1 year after filing lien.
Bonding permitted (Private): Yes, must be 125% of the lien value.
Statutory lien waiver form (Private): No.
Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Oklahoma since that date. Visit our 50-State Construction Law Map for information on other states.