Commencement notice (Private): No.
Completion notice (Private): No.
Preliminary lien notice (Private): Prime contractor - Required in contract with owner; Subcontractor - 8 days after commencing work.
Pre-lien notice (Private): Not required.
Lien claim (Private): 75 days after last furnishing labor/materials.
Deadline to file suit (Private): 120 days after filing lien; notice of intent to file suit required 10 days prior.
Bonding permitted (Private): Yes, must be the greater of 150% of the lien value or $1,000.
Statutory lien waiver form (Private): No.
Disclaimer: This information was published on January 1, 2020. Please contact Josh Levy, Eric Meier or Samantha Schacht for modifications made by Oregon since that date. Visit our 50-State Construction Law Map for information on other states.